Project Timeline

Find Out What’s Happening

With stage 1 of the project complete, and stage 2 commenced, there are many exciting progressions to be made in the coming months and years.

Phase 1
Project Preliminary Investigation
COMPLETE
DEC 2017
Phase 2
Project Development & Approvals
Stage 1
Preliminary Enviromental Assessment
SUBMITTED
MAR 2018
Stage 2
Environmental Impact Statement
TARGET SUBMISSION
MID-JUNE 2018
Stage 3
Development Application Approved
TARGET
SEPT 2018
Phase 3
Project Commitment
TARGET
DEC 2018
Phase 4
Stage 1
Construction & Commissioning
TARGET
JAN 2019
Stage 2
First Power Generation
TARGET
2 2020
Stage 3
Project Completion
TARGET
Q2 2021
Phase 5
Stage 1
Land Lease Expiry
2050
Stage 2
Decommissioning Period
2051